Speedily execute component projects of provincial Administrative - Political Center
-   +   A-   A+     20/02/2012
According to the Department of Construction, up to this time, the construction unit of the bidding package of technical infrastructure and landscape project has made 60-80% of the workload, expected to complete the project at the end of March. Currently, the investor directly conducted the contractor to mobilize manpower, facilities to concentrate on building projects to ensure the progress as the proposed plan.

Afternoon 16 February, Mr. Pham Quang Khai, Deputy Secretary of the Provincial Party Committee, presided over the meeting on the construction progress of the technical infrastructure and landscape of the provincial Administrative - Political Center. Mr. Tran Ngoc Thoi - Deputy Chairman of the provincial People’s Committee, representatives of departments, sections attended the meeting.

According to the Department of Construction, up to this time, the construction unit of the bidding package of technical infrastructure and landscape project has made 60-80% of the workload, expected to complete the project at the end of March. Currently, the investor directly conducted the contractor to mobilize manpower, facilities to concentrate on building projects to ensure the progress as the proposed plan.

After the report of the Department of Construction, Mr. Tran Ngoc Thoi requested the investor to promptly construct all the component projects of the provincial Administrative - Political Center, prevent delay of construction project for any reason. The provincial People’s Committee did not approve extension of contract performance period and price adjustment, payment for construction costs and other costs associated with the workload after 31March 2012.

Concluded at the meeting, Mr. Pham Quang Khai directed the Department of Construction, the Project Management must constantly be present at the construction site, solve difficulties and problems arising on time; speed up contractors to mobilize human resources and means of facilities to accelerate the construction schedule, specially draw attention of the investor to supervise, follow up closely the construction of verdure system at the provincial Administrative - Political Center.