Con Dao focus investment in key projects
-   +   A-   A+     19/07/2013
In the context of the general difficulties of the economy, to ensure gradual improvement of technical infrastructure, economic infrastructure, Con Dao District People's Committee chose to concentrate the resources for key projects that can bring advantages, promote development of industries and socio-economic sectors in the area.

In the context of the general difficulties of the economy, to ensure gradual improvement of technical infrastructure, economic infrastructure, Con Dao District People's Committee chose to concentrate the resources for key projects that can bring advantages, promote development of industries and socio-economic sectors in the area.

The total investment capital in 2013 for the development of Con Dao district is VND322.25 billion, of which the State budget capital is VND225.25 billion/64 projects. Source of capital from business and private businesses registered to implement capital construction investment in the province in 2013 is VND97 billion.

In the first 6 months of the year, Con Dao district disbursed more than VND 45 billion of budget fund for capital construction investment. Along with the disbursement of funds for investment projects, Con Dao district’s authorities regularly performed inspections and check the observance of the legislation in the field of construction and land law,  promptly stopped  and handled with cases of land encroachment, illegal construction; strengthened the exploitation management of stone and land resources that used as leveling materials and construction works, closely monitored to prevent adverse impact to the tourism landscape, environment and the ability of fresh water storage in the area.

According to the District People's Committee, the implementation of investment projects in the first 6 months got slow as compared to the plan, the value of disbursement only reached 14% of the total investment in 2013. The cause is difficulties of the economy, prices of construction materials, fuel, labor and other input costs highly increased to wait for adjusting the total investment, or for completion of site clearance and compensation; workforce of construction sector was scarce, it caused the delays, therefore, in the implementation of investment projects and construction progress of infrastructure projects.

In an attempt to ensure the disbursement of all funds invested in the development for the whole year, especially for budget fund, the Con Dao district’s People’s Committee required investors to accelerate the progress of projects; the district will have policies to attract workers in construction sector from other locals to work in Con Dao. In addition, the district will also facilitate in maximum foreign and domestic enterprises as well as individuals to implement all capital construction investment fund in the area as planned in 2013 with the amount of VND97 billion.

Mr. Le Xa - Chairman of the Con Dao District’s People’s Commit Chairman - says, “We have 64 projects - investment projects by budget fund have been implemented in the district. Along with solving difficulties and problems to speed up investment progress, the district also determines to focus all resources to perform projects - key works that have significance in promoting the development of economic sectors of the district, ensure ecological environment - environment, and better lives for people”.